Rhode Island Unveils Two-Step Process for Picking Washington Bridge Contractor

Officials will not when a new bridge will open, but plan to name the firm for the project by June 2025

Gov. Dan McKee speaks at a statehouse news conference on Oct. 15, while Chief of Staff Joseph Almond looks on.
Gov. Dan McKee speaks at a statehouse news conference on Oct. 15, while Chief of Staff Joseph Almond looks on.
Governor’s Office
Share
Gov. Dan McKee speaks at a statehouse news conference on Oct. 15, while Chief of Staff Joseph Almond looks on.
Gov. Dan McKee speaks at a statehouse news conference on Oct. 15, while Chief of Staff Joseph Almond looks on.
Governor’s Office
Rhode Island Unveils Two-Step Process for Picking Washington Bridge Contractor
Copy

More than 10 months after the abrupt emergency closing of the westbound Washington Bridge, Rhode Island state officials on Oct. 15 unveiled a revised process for picking a firm to build a new bridge.

Rhode Island transportation officials issued a request for qualifications for companies interested in building the new westbound bridge, and plan to choose two finalists from those applicants in December.

During a Statehouse news conference, state Department of Transportation Director Peter Alviti said the two-step process would result in a highly qualified company and the best design, price and schedule for completing the new span.

“We expect to have the two most qualified companies selected in December through the qualifications process,” Alviti said. “And a final company selected by June (2025), with a notice to proceed to work by July.”

The finalist who is not selected will receive a $1.75 million “stipend” for costs associated with creating its proposal. After a previous RFP failed to attract any bids, the governor’s office said it learned that companies are often discouraged from making such bids due to the expense.

Gov. Dan McKee conceded that the previous RFP process could have been better, and said he recognizes that businesses and motorists are still dealing with the impact of closing the westbound bridge last December.

McKee declined to estimate when a new bridge might open. Previous plans called for a new bridge by the fall of 2026, which now appears unlikely.

This story was reported by The Public’s Radio. You can read the entire story here.

Common Cause says decision shows need for clarity on 2016 law
After 7 failed restoration plans, CRMC to consider enforcement Tuesday over unauthorized rock wall
With the federal shutdown of the 988 “press 3” service for LGBTQ+ youth, Samaritans South Coast and Rhode Island’s call center are expanding culturally competent training to fill the gap in suicide prevention care
A federal judge struck down a rule allowing the National Endowment for the Arts to disfavor projects tied to ‘gender ideology,’ siding with Rhode Island Latino Arts and three other groups in a case brought by the ACLU
From Providence parks to coastal byways, Rhode Island’s fall foliage season is about to burst into color — with peak leaf-peeping expected in mid-to-late October across the Ocean State
A federal judge blasted the Trump administration’s halt of the $5 billion offshore wind project as “arbitrary and capricious,” clearing the way for Ørsted to restart work on the 65 turbines already 80% complete