New Washington Bridge Expected by November 2028

The state expects the project to cost up to $427 million, Rhode Island Gov. Dan McKee said.

Cars travel on the reconfigured eastbound span of the Washington Bridge. A new $427 million westbound span is slated for completion by November 2028.
Cars travel on the reconfigured eastbound span of the Washington Bridge. A new $427 million westbound span is slated for completion by November 2028.
David Lawlor/Rhode Island PBS
Share
Cars travel on the reconfigured eastbound span of the Washington Bridge. A new $427 million westbound span is slated for completion by November 2028.
Cars travel on the reconfigured eastbound span of the Washington Bridge. A new $427 million westbound span is slated for completion by November 2028.
David Lawlor/Rhode Island PBS
New Washington Bridge Expected by November 2028
Copy

The westbound Washington Bridge that carries I-195 is expected to be rebuilt by November 2028, Rhode Island Gov. Dan McKee said Friday, setting a target for a return to normalcy for Rhode Island drivers.

The state picked the Chicago-based Walsh Construction Company to construct a new westbound span and expects the project to cost up to $427 million, McKee said.

The announcement comes a year and a half after the sudden shutdown of the bridge that carried roughly 90,000 cars a day across the Seekonk River from East Providence to Providence.

After initially planning to repair the faulty bridge, the Rhode Island Department of Transportation contracted the Aetna Bridge Company to demolish it for $97 million. In the interim, RIDOT reconfigured the eastbound span to carry traffic in both directions.

A 2024 review by a Connecticut-based engineering firm suggested the new bridge could open between March and September of 2026. The engineering firm McNary, Bergeron & Johannsen said initial cost estimates pegged the price of the project at $250 million to $300 million.

Last August, the state sued 13 companies involved in work on the shuttered bridge, and has largely been tight-lipped about the problems that caused the closure. In May, an investigation by The Public’s Radio and Rhode Island PBS found that RIDOT may have missed critical signs that could have warned of the bridge’s deteriorating condition years before it was forced to close the bridge.

This is a developing story and will be updated.

Applications are due April 13, 2026
The Rams received a bid to March Madness. She received a bid to the University of Florida
This week on Possibly, we’re taking a closer look at how plastics have given the fossil fuel industry a new business platform — with hardly anyone noticing they’re even in the market
A family tradition from southern Italy has grown into a culinary calling card for a Rhode Island community
Charged with turning around a struggling Florida program, the three-time A-10 Coach of the Year leaves URI after a historic run that delivered a school-record 28 wins and the Rams’ first NCAA tournament berth in three decades
It takes around 40 gallons of sap to make just one gallon of syrup