MassDOT Unveils Early Plan to Replace New Bedford-Fairhaven Bridge

The new bridge would take less time to open and close for boat traffic than its 120-year-old predecessor, but a preliminary design revealed last week has left many uninspired

A rendering of the new bridge would replace the 120-year-old bridge connecting New Bedford and Fairhaven.
A rendering of the new bridge would replace the 120-year-old bridge connecting New Bedford and Fairhaven.
MassDOT
Share
A rendering of the new bridge would replace the 120-year-old bridge connecting New Bedford and Fairhaven.
A rendering of the new bridge would replace the 120-year-old bridge connecting New Bedford and Fairhaven.
MassDOT
MassDOT Unveils Early Plan to Replace New Bedford-Fairhaven Bridge
Copy

During the day, traffic on the New Bedford-Fairhaven bridge comes to a halt once an hour.

The 120-year-old steel bridge slowly spins 90 degrees until it’s perpendicular to the road, opening up a pair of narrow channels on both sides for fishing boats and barges to squeeze through.

Cars don’t start moving again until the bridge groans back into place. The whole process stops traffic for an average of about 12 to 23 minutes depending on how many boats are steaming by, according to a recent navigational study submitted to the Coast Guard.

The Massachusetts Department of Transportation is now developing a detailed proposal for a bridge replacement before legislators go back to the governor to ask her to issue the bond.

Last Thursday, MassDOT officials presented a bare bones rendering of the type of bridge they want to build. A pair of new steel towers would essentially lift a stretch of road up like an elevator. The new vertical lift bridge would open faster than the current swing bridge and create a navigational channel that’s twice as wide, enabling boats to pass through faster and traffic to get moving sooner.

This story was reported by The Public’s Radio. You can read the entire story here.

Bravo drops trailer and sets premiere date for Thursday, April 2, at 9 p.m.
Karen Greco confirmed that an undisclosed number of employees received forms that were ‘populated with incorrect information’
As Rhode Island’s most productive quahogging area prepares to reopen Feb. 9, frozen bays and brutal cold threaten livelihoods across the fleet
We’re switching it up this week and highlighting the events that fly under the radar because they’re always happening. Consider these our weekly Rhode Island favorites
After approving $350 million in borrowing to build two new high schools, voters declined to authorize an additional $50 million bond
Sojourner House CEO Vanessa Volz on housing, funding, and the limits of current responses