New Washington Bridge Expected by November 2028

The state expects the project to cost up to $427 million, Rhode Island Gov. Dan McKee said.

Cars travel on the reconfigured eastbound span of the Washington Bridge. A new $427 million westbound span is slated for completion by November 2028.
Cars travel on the reconfigured eastbound span of the Washington Bridge. A new $427 million westbound span is slated for completion by November 2028.
David Lawlor/Rhode Island PBS
Share
Cars travel on the reconfigured eastbound span of the Washington Bridge. A new $427 million westbound span is slated for completion by November 2028.
Cars travel on the reconfigured eastbound span of the Washington Bridge. A new $427 million westbound span is slated for completion by November 2028.
David Lawlor/Rhode Island PBS
New Washington Bridge Expected by November 2028
Copy

The westbound Washington Bridge that carries I-195 is expected to be rebuilt by November 2028, Rhode Island Gov. Dan McKee said Friday, setting a target for a return to normalcy for Rhode Island drivers.

The state picked the Chicago-based Walsh Construction Company to construct a new westbound span and expects the project to cost up to $427 million, McKee said.

The announcement comes a year and a half after the sudden shutdown of the bridge that carried roughly 90,000 cars a day across the Seekonk River from East Providence to Providence.

After initially planning to repair the faulty bridge, the Rhode Island Department of Transportation contracted the Aetna Bridge Company to demolish it for $97 million. In the interim, RIDOT reconfigured the eastbound span to carry traffic in both directions.

A 2024 review by a Connecticut-based engineering firm suggested the new bridge could open between March and September of 2026. The engineering firm McNary, Bergeron & Johannsen said initial cost estimates pegged the price of the project at $250 million to $300 million.

Last August, the state sued 13 companies involved in work on the shuttered bridge, and has largely been tight-lipped about the problems that caused the closure. In May, an investigation by The Public’s Radio and Rhode Island PBS found that RIDOT may have missed critical signs that could have warned of the bridge’s deteriorating condition years before it was forced to close the bridge.

This is a developing story and will be updated.

Still no news on McKee’s request for face time with Trump
For North Providence history teacher Tina O’Brien, studying the past makes ‘you feel more connected to the world around you’
Seasonal increases, end of COVID-era debt repayment terms pose a double whammy for vulnerable R.I. Energy customers
After three bat sightings in August — including one that prompted a weeklong office closure — union workers say the Providence building is unsafe, urging state officials not to renew DCYF’s 10-year lease
Commission holds public hearing on separate proposals to increase cap on gift values and apply limit to certain lobbyists
Gov. McKee responds by criticizing Foulkes over opioids